Geophysical and technical surveys for petroleum and gas
What's new
A new practice direction and data submission templates are available below. Read more about new reporting requirements and implementation timelines.
You must notify us before you conduct a seismic, scientific or technical survey and after you have completed the survey. You also need to provide a report after you complete your survey.
Read how to meet your notification and reporting obligations under Queensland resources legislation, and download a flowchart of reporting requirements for geophysical and technical surveys (PDF, 121KB).
Permits this applies to
- Authority to prospect
- Petroleum lease
- Data acquisition authority
Before starting activities
Check requirements for land access and other notices before starting petroleum and gas activities.
How to lodge your notices and reports
The table below shows what you need to submit and how to do it. If you need more help:
- refer to the legislation (references in the table below)
- read the Practice direction 6 – petroleum and gas reporting (PDF, 2.8MB) and use the Petroleum and gas data submission template (XLS, 774KB)
- read about lodging reports into the GSQ Lodgement Portal
- Use GSQ Lodgement Portal forms for some notices and data submission.
| Report/notice and legislation | When to lodge | How to lodge |
|---|---|---|
|
Notice of intention to carry out seismic survey or scientific or technical survey (General Regs1 s. 31) | At least 10 days before starting |
Lodge online form - Survey Notification or Report -intended, through GSQ Lodgement Portal. A copy of this notice must be given to each owner or occupier to which this activity relates (General Regs s28) |
| Notice of completion of seismic survey or scientific or technical survey (General Regs s. 32) | Within 10 days of completion | Lodge online form - Survey Notification or Report - completed, through the GSQ Lodgement Portal A copy of this notice must be given to each owner or occupier to which this activity relates (General Regs s28) |
|
Scientific and technical survey report (General Regs s. 39) | Within 2 years of completion |
Follow Practice direction 6 – petroleum and gas reporting. Lodge online form - Survey notification or report – submission, through the GSQ Lodgement Portal |
|
Seismic survey report (General Regs s. 38) | Within 2 years of completion | Follow Practice direction 6 – petroleum and gas reporting and use the data submission template, above. Upload all files to the GSQ Lodgement Portal. |
1General Regs: Petroleum and Gas (General Provisions) Regulation 2017